Your program has 121 stakeholders that you'll need to communicate with. Your communications
management plan defines how the communication should happen, what should be communicated,
and the expected modality of the communications. You'll also need which one of the following as an
input to the information distribution process in your program?
Question No 2
What is the formula to determine earned value (EV) for a program?
Question No 3
Olive is the program manager for her organization. She has created a request for proposal for a large
portion of her program. In this work to be procured she has set several requirements for the vendors
to participate. The chief among these requirements is a vendor must have at least four licensed
electricians in his team. This requirement for four licensed electricians is an example of which one of
the following terms?
Question No 4
You are the program manager for your organization. Management has asked you to create a
document that will capture the stakeholders concerns, perceived threats, and specific objectives
about the program and its
projects. What document is management asking you to create in this instance?
Question No 5
You are the program manager of the NHQ Program. You are working with your program team to
ensure that the work in the program is done accurately and according to scope. You are also
reviewing the team inspection process that will need to be done to ensure that the work is being
done according to the scope. If the work is found to be defective it will need to be corrected before
the program customers can inspect the work. What process are you completing to ensure that the
work is done accordingly to scope?